INTRODUCTION:
An incentive scheme may
be viewed as a winwin solution between the administration and the staff of
an organization. The advantages for the administration are: no requirement of
additional man power, higher and efficient machine utilisation, more
productivity, less pilferage of working hours, etc. Whereas for workers: it gives the
satisfaction of earning more by working more leading to more purchasing
power. And as an end result the organization is benefited with better
industrial relations and discipline.
In this write up, an
attempt has been made to discuss the existing incentive schemes on Indian
Railways without going into too much of technicalities but concentrating on the
conceptual aspects of the schemes.
PRESENT SCHEMES:
Presently existing
incentive schemes on Indian Railway workshops may be broadly grouped into two
categories:
One is based on saving of time in each activity by
the employee, there by performing the activity in lesser time than the
prescribed time- giving scope for increased out turn. (Chittaranjan pattern)
The other one is
directly linked to outturn given by a group. This is Group based incentive scheme.
(Tirupathi scheme) which has been introduced on workshops during January 2002.
CHITTARANJAN PATTERN
SCHEME
To appreciate better the
newly introduced incentive scheme in CRS,
(Carriage Repair Shop) Tirupathi, by bringing out
the differences with the existing schemes, the chittaranjan pattern is also
discussed briefly here under.
The time office has to
give every month the statements showing the number and details of workers in
each category for calculating the incentive earned.
THE RETHINKING:
There has been a general
view that the chittaranjan pattern of incentive scheme is not working up to the
expectations because of the following reasons:
·
Individual employee may earn the incentive leading to financial out flow
for the administration but final out turn of the workshop is not increasing.
·
There is no provision to take care of quality aspect of the work.
·
As this is an individual based scheme, the expected synergy in gaining
final output is not accruing.
·
There is a perceived scope for manipulation of time saved by the
employee.
The lacunae in the chittaranjan pattern
forced the administration to rethink- and hence no incentive scheme has been
introduced for workshops set up after 1980.
Hence the new scheme,
which is group based and is directly linked to outturn given by the group.
TIRUPATHI PATTERN OF
INCENTIVE SCHEME:
RITES Study group was
constituted to propose a new incentive scheme for the workshops on Indian
railways, Tirupathi workshop as a pilot project. The Railway Board with some
modifications accepted the RITES report. The similar scheme suggested by the
RITES study group is being implemented in production shops DLW and ICF. However
for the first time this scheme is introduced on workshops in Carriage Repair
shop
Tirupathi,
during January 2002, which was inaugurated by the Honorable Railway
Minister Shri Nitish Kumar.
Before discussing the
new scheme, the activities of CRS Tirupathi, are mentioned briefly:
The Production shops, support shops, and support
departments are given different incentive earning factors.
D) No Over Time:
E) Idle time:
Idle time can be booked only in the event of power
failure for more than one hour (unlike the chittaranjan pattern).
F)
Indicators of quality performance:
Rectification man- hours: If
a group is forced to spend more time than required to perform an activity
because of the low quality work/ incomplete work of the earlier group, the additional
time spent to rectify it, is called the rectification man hours and this factor
acts negatively on the incentive earned by the earlier group and the
individuals of that group.
G) QUALITY FACTORS:
i.e., if the value of these parameters increase the
incentive earned by the employee will decrease.
COMPARISON OF THE TWO SCHEMES:
|
THE CHITTARANJAN PATTERN
|
THE TIRUPATHI SCHEME |
|
1.Introduced on
workshops in 1958 2.It is individual
based incentive scheme 3.The time saved by
the worker in performing a work against the allowed time forms the basis for
the incentive earned. The maximum time that
can be saved to be eligible for incentive is 50% to the prescribed time for
an activity. 4. Idle time can be booked on more than one
reason like non availability of tools, machine break down, power cut etc
5.Over time is allowed 6.Quality factors are not taken into
consideration 7.There is no penalising factors for the
worker in earning the incentive for the poor quality of work, absence from
the workplace, 8.There are no equalizing factors for
different types of work.
|
1.Introduced on
workshops in January 2002 2.It is group based
incentive scheme. 3. It is directly linked
to out turn of the group in eGSCN units, and the attendance factors. The maximum % of
additional eGSCN coaches that can be turned out to be eligible for incentive
earning is 50% 4.Idle time can booked
only on account of power failure more than an hour.( In CRS it seldom happens
as power cut is managed by generators. 5. There is no
provision for over time in Tirupathi scheme as approved by the Railway board. (Even if Over Time is allowed as per RITES
Study, it works against the incentive earning capacity of the worker) 6.Quality factors are taken into
consideration and these if factors are adverse they act negative on the
incentive earned by the worker. 7.The important feature of this scheme is
that it takes into consideration of quality of work, the time spent away from
the work place; the rectification man-hours etc and these can act against the
amount of incentive earned by the worker. 8.All types of coachwork are converted into
eGSCN in case of coach works and in case of the turning of wheels the common
factor is ICF wheel sets.
|
THE WORKING OF THE SCHEME:
The theoretical aspects
have been discussed regarding the scheme in the earlier paragraphs. The actual
working details of the scheme will be discussed in the following paragraphs:
Prior to the introduction of the incentive scheme
CRS had been turning out 40coaches(80 Four wheeler Units) per month on an
average i.e., 480 coaches per year. This situation is termed as 100R condition
in RITES Study.
The Rly Board approved
incentive scheme is designed with an incentive earning of 20% i.e., 120R. With
the existing staff strength of 1030 the number of eGSCN that are to be turned
out to get 120R incentive is fixed at 50 equated GSCN coaches per month. If
less than this target is achieved, it will not be eligible for incentive
earning. However the upper ceiling limit of incentive as given in Para 4.02 of
Mechanical Code is applicable. i.e., more than 150R incentive is not
allowed. As per this, the maximum
additional out turn in eGSCN eligible for incentive would be restricted to 50%.
As
per RITES study, the Industrial
Engineering Department (IED) is made
responsible for the calculation of incentive and preparing the bill. While
preparing the bill the IED is supplied with inputs from Time office like the
total clocked in man hours of the various groups, and the absentee statements.
And IED collects details of various other data directly from the workshop like
the rectification man hours, the out turn. The bill prepared is sent to Accounts
Department along with the relevant documents for vetting. The vetted bill is
clubbed with the regular salary bill and payment is arranged after due internal
check by the Accounts department.
CRS has performed to its optimum and the out turn
has increased by 20 coaches per month on an average. Individual shops have
achieved maximum out turn to the tune of around150R in terms of eGSCN. As a
result the incentive payment was also at 150R.
The average incentive earned by
workers of various scales:(In Rs, for Carriage Fitting shop for 3 months from
Jan to March 2002 would give an idea of the amount of incentive payment to
various grades of staff.

FINANCIAL OUTGO OF INCENTIVES FOR THE
WORKSHOP-MONTHWISE (in Rs)
|
Month |
Production Shops |
Support Shops |
Support Department |
Supervisory Staff |
Total |
Outturn In Four wheeler Units (Not in SPUs) |
|
Jan-02 |
13,18,831 |
4,75,352 |
16,307 |
27,331 |
18,37,821 |
114 |
|
Feb-02 |
15,65,030 |
2,81,359 |
13,808 |
29,541 |
18,89,738 |
116 |
|
Mar-02 |
13,35,216 |
2,58,822 |
9,831 |
30,346 |
16,34,215 |
116 |
|
Apr-02 |
13,09,826 |
2,53,727 |
9,825 |
31,962 |
16,05,340 |
130 |
|
May-02 |
10,67,766 |
2,00,861 |
8,032 |
28327 |
13,04,986 |
124 |
|
Jun-02 |
12,97,817 |
2,59,789 |
9,161 |
30150 |
15,96,917 |
120 |
|
July-02 |
1412762 |
269077 |
11940 |
31088 |
16,93,779 |
134 |
|
Aug-02 |
1441087 |
283519 |
11819 |
29850 |
17,66,275 |
136 |
|
Total |
10748335 |
2282506 |
90723 |
208745 |
1,32,99,221 |
|
Note:
The incentive calculated is based on the eGSCN units (SPUs) turned out be individual groups. However the out turn shown in the last column is the total number of Four-wheeler Units dispatched by the workshop to the Traffic after the POH.
Prior to incentive scheme the average number of four-wheeler units turned out per month were 80. From January to March three months were trial period. During April there has been a slight enhancement of target by the RITES and hence the total incentive paid was reduced even the out turn was more compared to earlier three months.
And again during the
months of May and June due to heavy summer the percentage of absenteeism has
gone up. It was around 17% where as for other months it was around 12%
explaining the lesser amount of incentive earned by the workshop employees
though the out turn was matching compared to earlier months. Here we can
clearly observe the role of negative factors determining the amount of
incentive earned by the employee.

AN ANALYSIS AND CONCLUSION
This scheme will yield
good results provided there is a strict monitoring form the administration.
Various sub groups in the workshop have to work in tandem to achieve the
additional out turn for the workshop. Other wise there is a possibility of the
situation where in some groups in the workshop achieve additional outturn and
hence additional incentive whereas some lag behind leading to no net additional
out turn for entire workshop taken together.
It is required to
maintain the additional feed constantly and continuously at an increased level.
Form the point of view of the workers; they should not be deprived of incentive
for want of additional feed to avoid inviting any labour problem.
There is a possibility
of premature POH to keep up the additional feed to the incentive shops.
On completion of one year
the scheme has to be analysed for the financial viability duly taking into
consideration the following aspects:
The
amount of additional out flow in terms of labour payment (incentive) and material, and the financial
benefit to the Railways in terms of the additional out turn in return and at
what cost.

Annexure
follows: Formulae.
Formulae
Equation 1
Group Std. Monthly Target =
Annual Target in
SPU
(No. of Working Days in a
month)*( No.of working Days in a Year)
Equation 2
Std Man-hours for the group in
the month =
0.875
* Strength @ 120 R * Working Hours in the month
Equation 3
Group Attendance Factor =
( Actual Clocked In
Hours) 0.875*
On Roll Strength * Working Hours in
month
Equation 4
Available Man Hours =
Clocked in Man Hours
Less idle time man hours
less
rectification man hours
actually clocked in the month by own group on items for which other supplyin
ggrouop agrees for rectification by own group
plus
(3* rectification work man hours by other receiving group on items earlier
dispatched by own supplying group to any other receiving group.)
Equation 5
Group Production Norm for the group in SPU
for the month
=(Group Std. Monthly Target * Available Man
Hours)
Std. Man Hours for
the group in the month
Equation 6
Group Base Output of the group in SPU=
0.833 * Group Production Norm
Equation 7
Group
Production Index =
(Group incentive eligible Dispatches) *( Group Holding Factor )*
(Group Attendance Factor)/Group Base Output
Equation 8
Plant Production Index = P Xa/Xb+qYa/Yb+rZa+Zb+
.
Xa
Ya Za =
Group
incentive eligible despattch in month for
different incentive production groups
Xb Yb Zb =
corresponding
group base out put for the month for different incentive production groups.
P q r = applicable
weightage factors for individual production groups.
Applicable weightage factors =
(Allowed Time at 100 R per
SPU) * ( Group standard monthly target in SPU)
Sum of( allowed Time* satandard monthly target)of All Shops
Equation 9
Gross Production Index =
(0.7 * Group production index) + (0.3 * Plant Production Index)
Equation 10
Individual Incentive Earned =
(GPI-1)
*( Incentive Earning Factor )
*( Actual Clocked in Hours of the Employee exluding time spent away from
work place)
/
( Total Working Hours of the Month).
INCENTIVE CALCULATION
FOR SUPPORT SHOPS
Equation 11
Standard Man Power Ratio for Support Shops:
Arithmetic
Sum of Authorised Strength of all Production Shops
![]()
Authorized Strength of Support Shops
Equation 12
Actual Man power ratio=
Actual
overall Strength of all Production Shops
![]()
Actual On roll Strength of Support Shops
Equation 13
Support Shops Incentive
Group Performance Efficiency=
Actual Man Power Ratio
Standard Man Power Ratio
Equation 14
Support Shops Incentive Linkage Factor= 0.8
(Constant)
Equation 15
Individual Support Shops Attendance Factor=
Actual Clocked In
Hours
0.875
* Over all Strength * working Days * Working Hours
Equation 16
Weighted Performance Index=
Sum of
(G.P.I. * Over all Strength + G.P.I * Over all Strength + .
)
Sum of (Actual Over all Strength of Production
Shops)
Equation 17
Incentive Earning by an employee=
(Weighted
Performance Index 1) * 0.8* Support
Shops Incentive Group Performance Effy *
Individual support shop attendance
Factor * Applicable Incentive Earning
Factor * Clocked-in Hours by a member / Scheduled Working Hours.
Similar formulae
are given for the calculation of incentive for the support departments with
incentive linkage factor of 0.5.